The objectives to day are finish the bolts and barrel nuts installation on the long rails and work on the twin-vise install. NOTE: The pictures for this day contain extensive step by step notes. Please refer to them for any questions you might have regarding the details of the installation noted below. First the bolts […]
Workbench TWO – Day 24
Objectives for today are trimming the drawbore peg, drilling pre-drill holes for lag screws and sizing, cutting tenons and fitting the long rails. Trimming the drawbore pegs was a first for me. I used the Veritas Flush-Cutting saw. The cut was amazing. A little experimentation to hold the saw very flat and I […]
Workbench TWO – Day 23
Workbench TWO – Day 22
Objective today is complete the short rails mortise and tenons for for 2nd set of legs. Start installation of twin vise including cutting clearance in upper rail, sizing and initial fitting of backer boards for twin vise. Completing the remaining mortise and tenons for the short rails was straight forward. Learned a lot on […]
Workbench TWO – Day 21
Workbench TWO – Day 20
The objective for today is mortises for the legs. The leg tenons have been cut but need the mortises. Since this needed exact registration, I decided to make a router template and cut the mortise using a Whiteside Ultimate Trim bit. This is a very robust and smooth cutting bit. So this will be a […]
Workbench TWO – Day 19
Workbench TWO – Day 18
Workbench TWO – Day 17
Objective for today is four square the workbench top. Really !! This all started when I had completed the flattening of the bottom of the workbench and all the milling and mortise work on the legs. At that point I realized I could start positioning the legs and maybe connect the short rails into […]